Replacement windows in a brick facade

Whole-house window replacement with new exterior trim and finished interior returns

Location
Alexandria, VA
Completed
March 2025
Duration
1 day on site + 6 days + 4 days
Category
Windows
Representative brick home facade with precisely fitted dark bronze replacement windows

Representative concept image — not a customer project photograph

Representative project.This record describes the scope, materials, and construction method of work we carry out. It is not a specific customer’s completed job, and the photography has not been shot yet. Ask to see finished work in person.

Overview

Fourteen windows replaced across a brick facade, with the exterior trim renewed and every interior return re-finished rather than patched.

Most of the value in a window replacement is invisible from either side: the sill pan, the flashing sequence, the air seal, and the shimming that keeps the unit square.

What the owners wanted

  • Replace units that were no longer sealing
  • Keep the character of the facade
  • Finish the interiors properly rather than caulking a gap

Services performed

  • Window measurement and ordering
  • Removal and disposal
  • Installation, flashing, and air sealing
  • Exterior trim
  • Interior returns and casing

Materials used

Exterior
New trim, flashing, and sealant
Request something similar

Existing conditions

What we found

  • Original units with failed seals and rotted exterior trim
  • Interior returns previously patched with several different profiles

Design direction

The decisions that shaped it

  • Match the existing sightlines and divided-lite arrangement
  • One consistent interior casing profile throughout

Problem solving

What had to be worked out

Challenges

  • Brick openings vary. Every opening had to be measured individually rather than ordered as a set.
  • Two openings had concealed water damage that was only visible once the old units came out.

How they were solved

  • Each opening was measured and recorded separately, and units were ordered against that schedule.
  • The damaged framing was repaired and documented with photographs before the new units went in.

How it was built

Construction sequence

  1. 01

    Survey

    Measure and schedule every opening individually.

  2. 02

    Removal

    One elevation at a time so the house is never widely open.

  3. 03

    Installation

    Sill pan, flashing sequence, shim square, air seal.

  4. 04

    Finishing

    Exterior trim, interior returns, casing, and paint preparation.

Timeline on site

Survey and ordering
1 day on site
Installation
6 days
Trim and finishing
4 days

Working days on site, excluding material lead times and the days between trades.

Finished

The completed room

The interior return and casing finished around a new window
The interior return and casing finished around a new window

Your project

Something like this, in your house.

Tell us about the room and we will tell you what is involved, what it is likely to cost, and how long it would take.

Have photographs or a drawing? Upload them with your request — it usually saves a visit.